Dear dad,
The long awaited transformer is finally up in Minja. They have installed it this evening, see photos in attachment.
What next?
1. Commissioning will be done tomorrow, will share details after
2. We cannot yet use the power
3. The contractor has now placed his request for the final payment (shillings 17,815,109= including VAT) before he can connect electricity to the building!
We are very eager to finally begin to use power in Minja. Thank you so much for your tireless effort to sponsor Grace community. God bless.
Request;
You told me that you wrote another book, if you already have an English translation, will you please come along with one for me.
Very grateful and see you soon,
Son